The Key Process Areas for Level 2:Repeatable
----Requirements Management
Goal 1 System requirements allocated to
software are controlled to establish
a baseline for software engineering
and management use.
Goal 2 Software plans, products, and
activities are kept consistent
with the system requirements
allocated to software.
----Software Project Planning
Goal 1 Software estimates are documented
for use in planning and tracking
the software project.
Goal 2 Software project activities and
commitments are planned and
documented.
Goal 3 Affected groups and individuals
agree to their commitments related
to the software project.
----Software Project Tracking and Oversight
Goal 1 Actual results and performances
are tracked against the software
plans.
Goal 2 Corrective actions are taken and
managed to closure when actual
results and performance deviate
significantly from the software
plans.
Goal 3 Changes to software commitments
are agreed to by the affected
groups and individuals.
----Software Subcontract Management
Goal 1 The prime contractor selects
qualified software subcontractors.
Goal 2 The prime contractor and the
software subcontractor agree
to their commitments to each
other.
Goal 3 The prime contractor and the
software subcontractor maintain
ongoing communications.
Goal 4 The prime contractor tracks the
software subcontractor's actual
results and performance against
its commitments.
----Software Quality Assurance
Goal 1 Software quality assurance
activities are planned.
Goal 2 Adherence of software products
and activities to the applicable
standards, procedures, and
requirements is verified
objectively.
Goal 3 Affected groups and individuals
are informed of software quality
assurance activities and results.
Goal 4 Noncompliance issues that cannot
be resolved within the software
project are addressed by senior
management.
----Software Configuration Management
Goal 1 Software configuration management
activities are planned.
Goal 2 Selected software work products are
identified, controlled, and available.
Goal 3 Changes to identified software work
products are controlled.
Goal 4 Affected groups and individuals are
informed of the status and content
of software baselines.
-- ※ 来源:.月光软件站 http://www.moon-soft.com.[FROM: 61.129.21.24]
|
|