发信人: peteryeah() 
整理人: leeyg(2001-06-05 22:59:05), 站内信件
 | 
 
 
The Key Process Areas for Level 2:Repeatable
 
 ----Requirements Management
 Goal 1 System requirements allocated to
        software are controlled to establish
        a baseline for software engineering 
        and management use.
 
 Goal 2 Software plans, products, and 
        activities are kept consistent 
        with the system requirements 
        allocated to software.
 
 
 ----Software Project Planning
 Goal 1 Software estimates are documented
        for use in planning and tracking
        the software project.
 
 Goal 2 Software project activities and 
        commitments are planned and 
        documented.
 
 Goal 3 Affected groups and individuals 
        agree to their commitments related
        to the software project.
 
 
 ----Software Project Tracking and Oversight
 Goal 1 Actual results and performances 
        are tracked against the software
        plans.
 
 Goal 2 Corrective actions are taken and 
        managed to closure when actual 
        results and performance deviate 
        significantly from the software 
        plans.
 
 Goal 3 Changes to software commitments 
        are agreed to by the affected 
        groups and individuals.
 
 
 ----Software Subcontract Management
 Goal 1 The prime contractor selects 
        qualified software subcontractors.
 
 Goal 2 The prime contractor and the
        software subcontractor agree
        to their commitments to each
        other.
 
 Goal 3 The prime contractor and the
        software subcontractor maintain
        ongoing communications.
 
 Goal 4 The prime contractor tracks the 
        software subcontractor's actual 
        results and performance against 
        its commitments.
 
 
 ----Software Quality Assurance
 Goal 1 Software quality assurance 
        activities are planned.
 
 Goal 2 Adherence of software products 
        and activities to the applicable 
        standards, procedures, and 
        requirements is verified 
        objectively.
 
 Goal 3 Affected groups and individuals
        are informed of software quality
        assurance activities and results.
 
 Goal 4 Noncompliance issues that cannot
        be resolved within the software 
        project are addressed by senior 
        management.
 
 
 ----Software Configuration Management
 Goal 1 Software configuration management
        activities are planned.
 
 Goal 2 Selected software work products are
        identified, controlled, and available.
 
 Goal 3 Changes to identified software work 
        products are controlled.
 
 Goal 4 Affected groups and individuals are 
        informed of the status and content 
        of software baselines.
 
 
  -- ※ 来源:.月光软件站 http://www.moon-soft.com.[FROM: 61.129.21.24]
  | 
 
 
 |